Solar Carport Project Process: The 5 Phases
How a commercial solar carport project typically runs in the UK, from feasibility to switch-on. A standard project often takes 16-28 weeks end to end, but planning, the grid connection offer and equipment lead times set the real timetable, so treat every duration here as typical, not guaranteed.
1
Feasibility (typically weeks 1-2)
- A site visit by the installer or a surveyor
- Structural and irradiance modelling
- Car park layout assessment
- Indicative system size and capex range
- ROI modelling — simple and after-AIA payback
- A written feasibility report: ask when it will be delivered and whether it is charged for
2
Design & Consents (typically weeks 2-18)
- Concept to detailed structural and electrical design
- Planning: prior approval under Class OA in England where it applies, otherwise a full application to the local planning authority
- DNO G99 connection application (and G100 if needed)
- Building regulations submission
- Heritage / Conservation Officer consultation if relevant
3
Procurement & Build Commitment (typically weeks 18-22)
- Panel and inverter procurement: check which manufacturers are specified and what warranty terms they carry
- Steel-frame carport fabrication (a 6-10 week lead time is typical)
- EV charger procurement, if specified
- Battery storage procurement, if specified
- Finance drawdown (capital, asset finance or PPA)
- Final commit-to-build sign-off
4
Build & Commissioning (typically weeks 22-28)
- Site mobilisation, welfare and a Traffic Management Plan
- Pad-and-screw or driven-pile foundations (typically 1-2 weeks)
- Steel frame erection (typically 1-2 weeks)
- PV panel installation and DC cabling (typically 1-2 weeks)
- AC commissioning, G99 protection relay testing and DNO sign-off
- Monitoring portal setup, handover and training, plus an MCS certificate where the system falls within the scheme
5
Operate & Maintain (year 1 onwards)
- Day 1: switch-on and handover documentation
- An optional long-term O&M contract: ask for the scope and the price per kWp per year in writing
- Typical O&M scope: annual panel cleaning (de-ionised water brush) and quarterly remote monitoring with a fault-response commitment
- Panel and inverter warranty claims, usually managed through the installer or O&M provider
- Year 10 inverter replacement planning (panels remain under warranty to year 25)
- End-of-life decommissioning planning around year 23-24
Questions to ask an installer about the process
- Who will act as principal contractor and principal designer under CDM 2015?
- Which phases does the quoted price include, and which items are provisional sums?
- What does the programme depend on: the planning decision, the DNO connection offer and the steel and panel lead times?
- How will construction be sequenced so the car park can keep trading?
- What documents are handed over at completion: commissioning certificates, warranties, as-built drawings and the monitoring login?
Tell us about your car park
Send the details below and we reply by email. The answers help us reply with something relevant to your site.
Solar Car Parks is an independent information site published by SEO-DONS LTD. We are not an installer. We use your details to answer your enquiry; see the privacy notice.